CLIENT: POMELLATO
DURATION:
28 WEEKS
LOCATION:
BOND ST, LONDON
Key Aspects:
-
Demolition of existing roof, stairs and floors
-
Structural steelwork to accommodate new floor layout
-
New roof installation
-
Full fit out of front and back of house areas
Project Summary:
Working with the Italian Architects, SD undertook a complete refurbishment of the building which involved the structural remodelling and fitting out of a high-end jewellery boutique, spread over 5 storeys including offices and included removal of the roof, stairs and all the floors from the basement to the fourth floor.
There were a number of key matters that were important to our client during the project:
Project finish date
Quality of the work
Ensuring that neighbouring businesses- which included the Richard Green Gallery and Sotheby’s auction rooms - suffered no loss of revenue or prestige.
In order to achieve the project objectives, the shop fit-out was started whilst the structural works were still ongoing; although this is not unusual in the industry it is something which always requires careful planning and scheduling.