top of page
Screenshot 2024-08-16 at 14.57_edited.png

CLIENT: POMELLATO

DURATION:

28 WEEKS

LOCATION:

BOND ST, LONDON

Key Aspects:

  • Demolition of existing roof, stairs and floors

  • Structural steelwork to accommodate new floor layout 

  • New roof installation 

  • Full fit out of front and back of house areas 

Project Summary:

Working with the Italian Architects, SD undertook a complete refurbishment of the building which involved the structural remodelling and fitting out of a high-end jewellery boutique, spread over 5 storeys including offices and included removal of the roof, stairs and all the floors from the basement to the fourth floor.

 

There were a number of key matters that were important to our client during the project:

Project finish date

Quality of the work

 

Ensuring that neighbouring businesses- which included the Richard Green Gallery and Sotheby’s auction rooms - suffered no loss of revenue or prestige.

 

In order to achieve the project objectives, the shop fit-out was started whilst the structural works were still ongoing; although this is not unusual in the industry it is something which always requires careful planning and scheduling.

SD 1.png

Accredited by Construction Industry Training Board (CITB)             

CITB Logo.png

 Guild of Master Craftsmen                 

The-Guild-of-Master-Craftsmen1.jpg
SafeContractor_Seal_RGB.png
and Alcumus Safe Contractor

Copyright 2024 SD Shopfitting LTD | All Rights Reserved

Unit 1, Riverside Estate, Coldharbour Ln, Harpenden AL5 4UN | 01582 712160

bottom of page